On
February 6, the foundation stone was laid by the then
Minister for Fuel, Power and Natural Resources. By July,
the silhouette of the Refinery could be seen as it appears
today. In addition to this construction at Korangi,
it was necessary to build a Tank Farm at Keamari. There
the crude oil to be discharged from tankers in the Karachi
harbour could be stored, before being transferred to
the Refinery tanks at Korangi.
On October 28, the plant came into operation two months
ahead of schedule. It incorporates some of the most
modern refinery equipment and techniques. On November
14, the opening of the Refinery was performed by Field
Marshal Mohammad Ayub Khan, President of Pakistan. The
design capacity of the Refinery was to process 1 million
tons of crude oil annually, but that very year it was
decided to expand the capacity of the Refinery to 2.1
million tons per annum, as soon as possible after operations
had commenced.
|
 |